An Agile Team decides they want to use pair programming in future Iterations. Where should this be captured?

A. In the team retrospective notes

B. In the team’s improvement backlog

C. In the Inspect and Adapt meeting notes

D. In the Program Backlog

Correct Answer is

B. In the team’s improvement backlog

Explanation

The decision to use pair programming in future iterations should be captured in the team’s improvement backlog.

Here’s why this option is the most appropriate:

  • In the team retrospective notes: While the decision to adopt pair programming might be discussed and agreed upon during a retrospective, merely noting this decision in the retrospective notes might not ensure its implementation. Retrospective notes are important for capturing insights and decisions made during the meeting, but they are not always actionable or prioritized for future work.

  • In the team’s improvement backlog: This is the correct place to capture such a decision. The team’s improvement backlog is specifically designed to hold improvements, adjustments, and experiments the team plans to implement to enhance their processes and workflows. Capturing the decision to use pair programming here ensures that it is prioritized, tracked, and reviewed for effectiveness in future iterations. It makes the commitment more visible and actionable.

  • In the Inspect and Adapt meeting notes: The Inspect and Adapt (I&A) meeting is a SAFe event that occurs at the end of each Program Increment and involves the whole Agile Release Train. While it’s a venue for identifying larger-scale improvements, decisions about specific practices like pair programming, which are more tactical and team-specific, are best managed within the team’s domain, such as their improvement backlog.

  • In the Program Backlog: The Program Backlog is intended for features, enablers, and capabilities that require attention at the program level across multiple teams within the Agile Release Train. Decisions about specific engineering practices or process improvements within a single agile team, like adopting pair programming, do not typically belong in the Program Backlog. This backlog focuses on larger work items that impact the delivery of value at the program level.

By capturing the decision to use pair programming in the team’s improvement backlog, the team ensures that such process enhancements are considered, planned, and implemented systematically as part of their continuous improvement efforts.

Other SAFe Scrum Master Question – During Iteration planning, the Product Owner introduces multiple new Stories to the team. After a lot of discussion, the team decides to insert spikes into the Iteration for research. How should a Scrum Master help resolve this issue?

SPOCLEARN

Upskill and Reskill in industry-recognized certification courses to become a Global Professional.

Share
Published by
SPOCLEARN

Recent Posts

Unlocking the Power of SAFe®: Achieving Business Agility in the Digital Age

Discover how SAFe® empowers organizations with agility and speed, driving digital transformation and adaptability in…

8 mins ago

What is DevOps? Breaking Down Its Core Concepts

Explore DevOps fundamentals, key principles, and tools. Learn how DevOps fosters collaboration, automation, and continuous…

1 hour ago

The Evolution of Project Management: From Process-Based to Principles-Based Approaches

Explore how project management evolved from rigid processes to adaptable, principles-based approaches for greater flexibility…

1 day ago

Mastering ITIL and PRINCE2 for Enhanced Project Outcomes in Indian GCCs

Discover how ITIL and PRINCE2 enhance project outcomes in Indian GCCs, including adoption rates, training…

2 weeks ago

Exploring the Eight Project Performance Domains in the PMBOK® Guide: A Comprehensive Breakdown

Discover the eight essential Project Performance Domains outlined in the PMBOK® Guide. Learn how they…

2 weeks ago

What Are ITIL Management Practices?

Discover essential ITIL management practices, their types, and how they improve IT Service Management. Learn…

3 weeks ago