A. The ratio of tasks planned to tasks completed
B. Team member utilization as a percentage of total capacity
C. The ratio of Story points completed to Story points planned in the PI
D. The ratio of business value achieved to business value planned for the PI
In the context of the Scaled Agile Framework (SAFe), team performance is primarily measured by the ratio of Story points completed to Story points planned in the PI (Program Increment). This measurement reflects how effectively a team or Agile Release Train (ART) has delivered against its commitments throughout a PI.
Let’s briefly examine why this option is correct and why the others are less aligned with SAFe’s principles:
Therefore, the ratio of Story points completed to Story points planned in the PI is the most accurate reflection of team performance in SAFe, focusing on the completion of work and value delivery over merely being busy or completing a high number of tasks.
Other SAFe Scrum Master Question – Lee is a developer on the team. At every daily stand-up Lee reports, “Yesterday, I worked on indexing. Today, I will work on indexing. No impediments.”
Discover how SAFe® empowers organizations with agility and speed, driving digital transformation and adaptability in…
Explore DevOps fundamentals, key principles, and tools. Learn how DevOps fosters collaboration, automation, and continuous…
Explore how project management evolved from rigid processes to adaptable, principles-based approaches for greater flexibility…
Discover how ITIL and PRINCE2 enhance project outcomes in Indian GCCs, including adoption rates, training…
Discover the eight essential Project Performance Domains outlined in the PMBOK® Guide. Learn how they…
Discover essential ITIL management practices, their types, and how they improve IT Service Management. Learn…