A. Review Solution Architecture
B. Identify impediments
C. Facilitate cross-team collaboration
D. Collaborate release details with Systems Team
E. Discuss Program Backlog priority changes
The correct answer is
B. Identify impediments
C. Facilitate cross-team collaboration
Explanation
The two primary purposes of the Scrum of Scrums meeting are:
- Identify impediments
- Facilitate cross-team collaboration
Why these are correct
- Identify impediments: The Scrum of Scrums is a coordination meeting for representatives from multiple Scrum teams to discuss progress, plans, and problems. One of its key purposes is to identify impediments that affect more than one team. By bringing these to light in a shared forum, the teams can work together to find solutions, ensuring that obstacles to progress are addressed promptly and efficiently.
- Facilitate cross-team collaboration: This meeting serves as a platform for facilitating cross-team collaboration. It allows teams to share information about their work, and dependencies between teams, and coordinate efforts. This collaboration is essential for aligning the teams towards the common goals of the project or program, ensuring that integration points and dependencies are managed effectively.
Why the others are not as correct
- Review Solution Architecture: While discussions about solution architecture might occur in the context of addressing impediments or facilitating collaboration, reviewing solution architecture is not a primary purpose of the Scrum of Scrums meeting. Specific architectural discussions are usually handled in more focused meetings involving the relevant stakeholders and technical experts.
- Collaborate release details with Systems Team: Although collaborating on release details with the Systems Team is important, it is not a primary purpose of the Scrum of Scrums meeting. Release planning and coordination might involve separate meetings that include the Systems Team and other stakeholders to address the specifics of release management.
- Discuss Program Backlog priority changes: Discussing changes to the Program Backlog priorities is crucial within the context of PI Planning and other program-level events in SAFe (Scaled Agile Framework), but it is not a primary focus of the Scrum of Scrums meeting. The Scrum of Scrums focuses more on the operational coordination between teams rather than on strategic backlog prioritization, which is typically handled in other forums involving Product Owners and Product Management.
Other SAFe Scrum Master Question – A Scrum Master is frustrated that her team finds no value during Iteration retrospectives, and the team has asked that she cancel all future ones. Which two specific anti-patterns are most likely present within the team’s retrospectives? (Choose two.)